According to the calculating, the space required for on day’s production is around 200sqm, following sufficient air curing, the green building units are removed from the pallets to the next day, calculation of the total curingarea:200×1.5=300 sqm,workshop area for machine is around 250 sqm,total shaded area is around 550 sqm,Forstocking yard the requiredarea is around 2000 sqm( based on 28 days production)Note: land area mentioned includeds the area for raw material assembly, workshop, officeand assembly yard for complete products. we will ask for a map of customer's land dimension, then we will design a customized factory layout and make best use of your land.
A simple block making production line in the picture requires approximately 12-15 manual labors and 2 supervisors ( to operate the machine needs 5-6 employees)
One operator for batching station and mixer
One operator for block machine
2 operators for feeding pallets to the machine
1-2 operator for forklift
1.PL1200 batching station | 2.JS500 Mixer | 3.Cement silo | 4.screw conveyor |
5.Cement scale | 6.Conveyor belt | 7.block machine | 8.Automatic stacker |
www,unikblockmachine.com
Previous:How to make concrete colored pavers
Next:How to high pressure steam curing for green concrete product